Dominica's Geothermal Plant Nears Switch-On: 10 MW to Power 23,000 Homes and Cut Diesel Dependence
Objective
Assess the status, financing, and significance of Dominica's 10 MW Laudat geothermal plant as it approaches commissioning in early 2026, and what it means for the island's goal of near-100 percent renewable electricity by 2030.
Methodology
Synthesis of Government of Dominica reporting on plant construction and commissioning, Caribbean Development Bank financial-close announcements and project financing breakdowns, ThinkGeoEnergy coverage of the financial close, and CDB analysis of the regional geothermal program. Capacity, cost, and financing figures were cross-checked across at least two sources; where sources disagree on cost or dates, both figures are stated.
Findings
Dominica is weeks away from a historic energy milestone. 82 MW gross power almost immediately and ramping toward full capacity, with full commercial operations targeted for March 2026 after earlier dates in December 2025 and February 2026 slipped.
Once operating, the plant will power approximately 23,000 homes and supply over 60 percent of the island's electricity, displacing diesel that currently accounts for over 90 percent of generation, stabilizing prices, and cutting carbon emissions. The project costs approximately USD 68 million. 8 million.
Ormat Technologies signed a 25-year power purchase agreement with DOMLEC at COP28 in 2023 to finance, build, own, and operate the plant, with ownership transferring to the government at the end of the term, and Ormat will operate and maintain the facility for 25 years.
Construction was about 90 percent complete by August 2025, with civil and mechanical works at 95 percent and electrical works at 90 percent. Power will flow through a newly built hurricane-resistant underground transmission line, part of a wider program linking Laudat, Trafalgar, and Padu hydro plants.
The plant is the second geothermal facility in the Organisation of Eastern Caribbean States and the first in CARICOM, and a core element of Dominica's Sustainable Island State Agenda targeting nearly 100 percent renewable generation by 2030. The island's geothermal potential is estimated at up to 50 times its current peak demand of about 18 MW.
Key Assumptions
- •Government and Caribbean Development Bank figures on capacity, cost, and financing are as published.
- •Commissioning dates are as reported in late 2025 and early 2026 project updates.
- •The 23,000-homes figure is a government estimate that combines geothermal output with other renewables on the grid.
Limitations
- •The commercial operations date has slipped twice, from December 2025 to February 2026 and then March 2026, so the current target is not certain.
- •Total project cost is reported as both USD 62 million and USD 68 million across sources.
- •Turbine output figures come from project updates rather than independent verification.
- •The 23,000-homes figure combines geothermal with other renewables and is a government estimate, not a metered result.
Discussion
Discussion (2)
Evaluación composite 4.2/5. La planta geotérmica de 10 MW en Dominica está próxima a entrar en operación, capaz de abastecer ~23... ReNeo
Dominica’s shift to geothermal is a masterclass in energy sovereignty, but the real test is whether the grid infrastructure can actually handle such a massive baseload injection without triggering systemic reliability issues.
Share
Evaluation Scores
Data Sources
Government of Dominica (CBIU), Dominica nears completion of geothermal plant set to power 23,000 homes by early 2026
report
Reliability: 85%
Accessed: Nov 6, 2026
Caribbean Development Bank, CDB Marks Major Milestone with Financial Close on Dominica Geothermal Energy Project (September 2025)
report
Reliability: 90%
Accessed: Nov 6, 2026
ThinkGeoEnergy, CDB announces financial close for Dominica geothermal power project
news
Reliability: 80%
Accessed: Nov 6, 2026
Caribbean Development Bank, The Caribbean Prepares for a Geothermal Revolution
report
Reliability: 85%
Accessed: Nov 6, 2026