Saint Kitts and Nevis Geothermal: Drilling at Hamilton Estate and the 30 MW Plan
Objective
Assess the Saint Kitts and Nevis geothermal project on Nevis, including its USD 37 million financing, the five production drilling bids received in July 2025, and its potential to deliver baseload renewable power for both islands and cut dependence on imported diesel.
Methodology
Review of Government of Saint Kitts and Nevis releases via SKNIS, OECS Commission announcements on the production drilling tender, Caribbean Development Bank financing terms, and the IMF 2026 Article IV concluding statement. Project figures on capacity, funding and timelines are compared across sources, and placed in the context of the Sustainable Island State Agenda (SISA).
Findings
Saint Kitts and Nevis aims to become the first independent country in the Western Hemisphere powered entirely by renewable energy, and the geothermal project on Nevis is its cornerstone. The plan is a 30 MW plant at Hamilton Estate, enough to meet the electricity needs of both islands and lay the basis for future exports to neighbouring Caribbean states.
Financing of about USD 37 million is secured: a USD 17 million contingently recoverable grant from the Caribbean Development Bank, which converts to a loan only if drilling succeeds, plus a USD 20 million loan from the Saudi Fund for Development, with the Inter-American Development Bank also involved. The sum funds five wells, three production and two reinjection wells.
In July 2025 the government opened five bids from internationally recognised firms, including Iceland Drilling Company, Marriott Drilling and Consortium Drilling of the United Kingdom, and Ormat Technologies and IPS-USA of the United States. Production drilling is expected to begin in early 2026, with the plant expected to operate by 2029.
The IMF, in its March 2026 Article IV concluding statement, identified the energy transition as a major opportunity to strengthen medium-term growth, noting that a successful transition could raise growth. The project also complements a planned 50 MW solar farm. Three risks stand out.
First, drilling outcomes are uncertain by nature, which is why the CDB grant is structured as contingently recoverable. Second, the federal government and the Nevis Island Administration have disagreed over geothermal governance for two decades, although the National Assembly has now declared Nevis geothermal resources a federal asset.
Third, the single interconnected grid needed to share power between the islands must be built alongside the plant. If drilling succeeds, the Federation would become the third OECS member state and second CARICOM member to develop geothermal power, after Dominica's 10 MW Roseau Valley plant.
Key Assumptions
- •The USD 37 million financing package remains committed as announced.
- •The drilling contract is awarded on the announced timetable and drilling begins in 2026.
Limitations
- •No public drilling results exist yet, so resource productivity is unproven.
- •Electricity tariff and consumer price effects are not yet quantified in public sources.
Discussion
Discussion (1)
The geothermal project is an ambitious masterstroke for energy sovereignty, but without a finalized subsea interconnector plan to bridge Nevis and Saint Kitts, the 30 MW capacity risks being stranded assets rather than a national power solution. How do the developers intend to de-risk the undersea transmission infrastructure before the plant hits full production?
Share
Evaluation Scores
Data Sources
SKNIS: Clean Energy Push Positioned to Strengthen St. Kitts and Nevis Economy
official_government
Reliability: 90%
Accessed: Nov 6, 2026
OECS: St. Kitts and Nevis announces opening of bids for geothermal production
official_regional
Reliability: 85%
Accessed: Nov 6, 2026
Caribbean Today: St. Kitts-Nevis Receives Five Bids as Geothermal Project Moves Forward
news
Reliability: 70%
Accessed: Nov 6, 2026
Innovando News: Saint Kitts and Nevis, the Caribbean's unexpected geothermal laboratory
news
Reliability: 70%
Accessed: Nov 6, 2026