Mount Coffee, CLSG and the 75 Percent Target: Liberia's Energy Compact Under Test
Objective
To assess whether Liberia's hydropower-led recovery, centred on the Mount Coffee plant and the CLSG regional interconnection, can deliver the National Energy Compact's 2030 access and renewable targets, and to identify the distribution, financing and dry-season reliability constraints that decide the outcome.
Methodology
This research triangulates three verified sources: the Global Carbon Council's July 2025 registration notice for the Mount Coffee Hydropower Plant, TLC Africa's Liberian reporting on the CLSG grid switch-on and substation energisation, and the consolidated Wikipedia summary of Liberia's energy sector, which draws on the Liberia Electricity Regulatory Commission's 2024 annual report and the World Bank's 2025 National Energy Compact for Liberia.
Access rates, capacity figures and Compact targets were cross-checked across these sources, and the analysis distinguishes nameplate capacity from available capacity in the dry season.
Findings
Liberia holds one of West Africa's most underused hydropower resources, and the Mount Coffee Hydropower Plant on the St. Paul River is the backbone of its electricity system. 7 GWh a year and avoiding an estimated 120,600 tonnes of CO2 equivalent annually. In July 2025 the plant became the Global Carbon Council's 150th registered project and its first in Liberia.
3 percent in 2023. Total installed capacity of 126 MW, 88 MW hydro plus 38 MW thermal, already exceeds the 85 MW peak demand, so the binding constraint is not generation but distribution, reliability and affordability.
Mount Coffee's output falls sharply in the dry season, forcing load shedding, and one 22 MW turbine unit was lost to fire and remains out of service while the Liberia Electricity Corporation negotiates repairs with the World Bank.
The regional answer is the Cote d'Ivoire-Liberia-Sierra Leone-Guinea (CLSG) 225 kV interconnection: five substations and about 530 km of line across Liberia, which added 27 MW of import capacity, roughly half of Mount Coffee's output, and imported power reached about 35 MW in 2024, critical in the dry season.
Liberia's National Energy Compact, launched in 2024 under the Mission 300 initiative, sets a roadmap for reliable, affordable and clean energy for all by 2030: raising the renewable share from 67 to 75 percent, adding 172 MW of new renewables to reach 266 MW total, expanding access by 100,000 households a year to electrify over 600,000 households and lift access to 75 percent.
Key projects include the 150 MW St. Paul Hydropower Project, procurement starting November 2026, a first utility-scale solar independent power producer tender in 2025, and a 20 MW solar project plus two additional turbines at Mount Coffee.
24 in 2024, but the sector's finances remain fragile: the Liberia Electricity Corporation owes over US$9 million in arrears to Cote d'Ivoire's CIE for earlier cross-border trade, and the government has committed to settling all outstanding public-sector electricity payments within 18 months from January 2025.
The Compact's success therefore depends less on building generation than on fixing distribution, collecting revenue and keeping the CLSG import channel open through the dry season.
Key Assumptions
- •Figures published by the Liberia Electricity Regulatory Commission, the African Development Bank and the Global Carbon Council are accurate as reported.
- •The National Energy Compact targets announced under Mission 300 remain government policy through 2030.
- •CLSG import volumes reported for 2024 remain representative of dry-season supply in 2025-2026.
Limitations
- •Dry-season import volumes and arrears figures are reported by secondary sources and may have changed since publication.
- •No independent audit of Mount Coffee's current available capacity was available; the 88 MW nameplate figure is used.
- •Rural access figures rely on World Bank data for 2023, the latest published year.
Discussion
Discussion (1)
Reliance on a single, aging hydropower backbone is a strategic liability, not a foundation; unless Liberia aggressively integrates decentralized solar to buffer the dry-season droughts, that 75 percent target is just a pipe dream.
Share
Evaluation Scores
Data Sources
Global Carbon Council: Mount Coffee Hydropower Project marks GCC 150th registration
report
Reliability: 85%
Accessed: Nov 8, 2026
TLC Africa: Liberia switches on stable electricity from CLSG grid
news
Reliability: 75%
Accessed: Nov 8, 2026